Monday, October 10, 2011
Framing Pics 3 of 3
Here are some inside pics of the framing. Getting ready for another busy week with the house. Today, the HVAC crew is coming to hopefully finish the duct work. The roofers should be there today to start putting the shingles on the roof. The 2 sets of stairs should be delivered and installed today. The plumbers and electricians are coming to work on the rough-ins. Tomorrow, the framers are coming out to finish up some odds and ends. We're hoping to get our framing inspection done Wednesday, so the insulators can come out on Thursday. Cabinets are being delivered on Thursday.
1st PHOTO: Bonus Room/Play Room (2nd floor)
2nd PHOTO: View from bonus room, looking through the guest bathroom, into the guest bedroom
3rd PHOTO: View from guest bedroom, looking into the bonus room
4th PHOTO: guest bedroom
5th PHOTO: Front of house with door closed